When the keys are handed over for a property bought off-plan, it is common to find finishing defects or malfunctions that do not prevent you from living in the property.
In that case, the buyer benefits from a period during which they can require the developer to carry out these repairs.
These defects can be a source of conflict, because the buyer does not know their rights and the developer may play on the wording.
How long is the builder liable after the handover of the keys?
The Israeli Sale Law (Apartments) as applied since April 2011 provides that the developer’s liability continues after the handover of the keys, for a period set by law. This period varies according to the type of materials requiring repair. The law distinguishes between two main periods:
– The inspection period;
– The liability period.
The inspection period
At the handover of the keys from the developer to the buyer, a handover protocol is drawn up and signed by the Parties. It lists all the defects and malfunctions noted during the visit of the apartment. From that date, and for a period of up to seven years, the developer must carry out certain repairs, as follows:
– During the first year: Any construction defect found in the apartment that was not visible before. It is also necessary to refer to the terms of the purchase contract, because repairs are generally conditional on the buyer’s obligation to inform the developer in writing and as soon as possible;
– During the first two years: Defects affecting building materials and structures, as well as defects in interior coverings;
– During three years:
– Malfunctions of electrical appliances and machinery (generally in the common areas);
– Construction defects in outdoor areas;
– Subsidence of ground-floor surfaces, parking spaces, paths and pavements in the common areas;
– Significant finishing defects;
– Significant thermal insulation defects in the walls and the safe room.
– During four years:
Defects in the plumbing and wastewater drainage system, including sewers and gutters;
Waterproofing defects in the building, including the underground car park, walls, ceilings and roof.
– During five years: Significant cracks in the walls and/or ceilings.
– During seven years: In the event of significant deterioration or alteration of the exterior coverings.
These periods are set by law and cannot be shortened, even if the Parties wish to agree otherwise. However, the developer is exempt from any liability where the defects are not of its making and were, for example, caused by the buyer.
The guarantee period
Once the inspection period has ended, the guarantee period begins, lasting three years.
During this period, the developer’s repair obligation is limited to defects for which the buyer has proved that they result from poor workmanship directly linked to the construction or to defective materials.
In most cases, the developer is contacted if there are problems linked to construction errors in the foundations, in the concrete structure of the building, or defects that could not have been detected beforehand.